October 2024 → February 2025
Step 1 - Existing Conditions Assessment 
 
 
February 26 2025
Public Input Opportunity #1
 
 
February → June 2025
Step 2 - Opportunity Analysis 
 
 
June 11 2025
Public Input Opportunity #2
Location to be determined. 
 
 
July → September 2025
Step 3 - Recommendations and Implementation 
 
 
September 2025
Step 4 - Final Report and Project Delivery
 
 
October 31 2025
Project Finished